Let's say I have a project with three subtasks:
* TODO project [1/3]
:PROPERTIES:
:ORDERED: t
:END:
** DONE subtask1
CLOSED: [2020-04-05 Sun 15:12]
** TODO subtask2
** TODO subtask3
I have set the first item to DONE, and the progress entry shows [1/3] so it seems like org mode recognized the dependency. In the agenda todo view I now only want to see subtask2, because I cannot start working on subtask3 before it's done. However I now see both subtask2 and subtask3 in agenda todo. Is it possible to configure so that I only see subtask2 there?